- Barton Street project
-
Area impacted: St. James Parish
Expected start and end dates: July - November 2024
Approximate number of poles: 380
Approximate number of line miles: 10 - All project details, including start and end dates, are subject to change due to weather and other external factors.
- St. James Parish along Mississippi River
-
Area impacted: Capital Region
Status: Completed
Approximate number of poles: 348 - All project details, including start and end dates, are subject to change due to weather and other external factors.