Gonzales Permit Requirements

Within town limits Permit Office

City permit or inspection for:

 

Residential:

• New construction, permanent meter

• New construction, temporary meter

• Existing structure-if Entergy has to run a service line a permit is required

• Inactive 60 days

• Rewiring: such as upgrading service, relocation of service, changing out meter pan, etc.

 

Commercial:

• New construction, permanent meter

• New construction, temporary meter

• Existing structure-if Entergy has to run a service line a permit is required

• Inactive 60 days

• Rewiring: such as upgrading service, relocation of service, changing out meter pan, etc.

 

 

Ascension Parish Permit Requirements